K. Kowit, as discuss in meeting yesterday Tentative Schedule shipment is,
2nd. Feb. 2014 Ship production deck extension panel no. 1,2 and 3 also Ship loose members.
9th. Feb. 2014 Ship Mezzanine deck extension panel no. 1,2 also Ship loose and Instrument tubing access walkway panel, angle post and Handrail etc.
Fabrication and coating tentative will be complete on 23 Jan 2014.Please:-
-Follow-up steel structure at yard #3 blast/paint still left behind send to yard #2 asap. Also pipe handrail socket Dia. 2” STD.
-Send pipe handrail Dia. 1 ½” to hot deep galvanized.
-Order the angle bar and C-Channel for E&I support Ref. Dwg. S-0221
-Check lifting gears Cert. for certify to re-used.