Here is the outstanding list :
1. Onyx stone finish and drawing
2. Reception light - mockup of kryptonite set for Thurs 9 June. Need to close out alternative design by Friday 10 June. Concept already presented last Friday.
3. Breakout pendant lights x5 (need a cost from Vendor because this item not in budget)
4. Logo engraving, need to decide on beveled or not beveled. Struggle to find beveled engraver.
5. Armour coat finish needs selecting by Friday 10 June.
6. Reception breakout rug - already ordered, 4 wk lead time.
7. Breakout rug - waiting for the sample and confirm, need to let client know that this will be delay
8. Reception Desk dwg (& vase details) to be shared with A&O for final sign-off.
9. Stone Vase keep or not? Carcass ready but stone-vase mockup holding back cladding of desk.
10. Credenza & other joinery details (issue to choice by COB today)
11. Meeting table drawing (legs need approving, Tann will order cable management retractor ahead).
12. Area rug for staff break out. Sample due Fri 10 July & lead time is 8 weeks. Anticipated delivery mid-August
13. Barisol stretched ceiling artwork. Membrane ordered, photo taken but need to test mockup on site.
14. Floor box order - Tann to follow up.
15. Cipsol Fabric Ceiling - waiting for the photograph to be print, the fabric already ordered
16. Meeting room table x2 - design and outlet location to be confirm
17. Bathroom - drawing and sanitary list