Please be informed that the time frame for M-1 barge move to carry out anchor handling and personnel transfer as the below following :
Date 29-1-2016 - In the morning Pax transfer prior to commence anchor handling , 4 anchors and BDB retrieval at location BEWS, then evening Pax return to M-1 by barge crane or BEWS crane.
Date 30 -1-2016- In the morning Pax transfer prior to resume anchor handling , 4 Anchors retrieval at BEWS and noon time M-1 proceed to anchors deployment at Benchamas anchorage. then evening Pax return to M-1 by barge crane.
Date 31-1-2016 - In the morning Pax transfer prior to 4 anchors deployment at BEPP South and 4 soft line connections at BELQ & facility legs. At this stage required 2-3 FE crews to assist connect soft line on the jacket legs.