All,
Especially ZIEC and Tri-En , this is to have a strong remind you again on the following schedules,
- today (13th Dec) all works to kitchen areas must be finish, the hotel will start their cooking tomorrow, compensation shall be applied if this cannot finish. No worker allow to access this area starting from tomorrow.
- granite top counter must finish today, the coffee machine supplier will start their installation tomorrow. Compensation will be applied if cannot finish,
- The ADD must finish on 20th, the hotel will set up on 21st , then the first breakfast will serve on 22nd. Compensation to all hotel staffs salaries will be applied also if cannot finish.
- priority to complete all public toilets and staff toilets immediately,
- tomorrow (14th Dec) , the hotel will bring their furniture and set up reception office, must finish today
- lobby areas must have a actual door installed and clean within today.
If you cannot finish this above schedule, i cannot help you on the financial and work contents anymore, thanks
RHLB to please note the above conditions, thanks