After Aware solving the problem leakage of oil generator. Therefore process next, the installation of the electrical system for server room and check compatibility with UPS and found many problems with bad planning (Resolve problem that worked by trial and error every time) and poor design in many point. I think if we let them continues this operation like this may cause trouble in the future.
And there is a problem with one of my concern is power of generator machine that the Aware company offer, it may have insufficient consumption power of the electrical equipment in the server room. Because the last week I have receive a request to reduce the electrical equipment that uses electricity from a generator if have event power outage.
May I would like to meeting and discuss with you and present the facts about electrical power and operation on Monday, January 4, 2016 at 10:00 AM. If the day and time is not convenient for you, Please let me know. Therefore, an alternative appointment will be arranged. During this time I will stop working anything about the server room. In order to the conclusion of the meeting before continuing the process next.