SSafety stock for high risk items is planned for 1 month at both Renault and Nissan plus 1 month contingency at current site. Safety stock for low risk items is 14 working days plus 1 month contingency. Capacity at new facility will be 50% higher than current plant - see attached capacity plans and stock build / usage data for information.