As water leak into Motif shop by 5 contractor work (ITD, PISA, MECT, EG and KAD) make the shop cannot open on schedule (8th May 2014) but open on 28th July 2014.
Motif shop would like to request damage cost total 4,822,295.76 THB (Four million Eight Hundred Twenty two Thousand Two Hundred Ninety Five Baht Seventy Six Stang) according to attach file.
We considered the responsibility involve to Terrace area at level 5 above that shop. Therefore, we will share the responsibility of the damage cost as following;
- ITD 30% of damage cost due construction and waterproof system.
- PISA 30% of damage cost due Balustrade installation.
- MECT 15% of damage cost due Pipe or sleve and drain system.
- EG 15% of damage cost due Granite stone stuck drain system.
- KAD 15% of damage cost due drift, fertilizer and materials are block drain system.
As water leak into Motif shop by 5 contractor work (ITD, PISA, MECT, EG and KAD) make the shop cannot open on schedule (8th May 2014) but open on 28th July 2014.
Motif shop would like to request damage cost total 4,822,295.76 THB (Four million Eight Hundred Twenty two Thousand Two Hundred Ninety Five Baht Seventy Six Stang) according to attach file.
We considered the responsibility involve to Terrace area at level 5 above that shop. Therefore, we will share the responsibility of the damage cost as following;
- ITD 30% of damage cost due construction and waterproof system.
- PISA 30% of damage cost due Balustrade installation.
- MECT 15% of damage cost due Pipe or sleve and drain system.
- EG 15% of damage cost due Granite stone stuck drain system.
- KAD 15% of damage cost due drift, fertilizer and materials are block drain system.