We are requested on the phone that code G documents which have been approved by Owner should be sent as “for reference” not “for construction”.
However, this procedure is not clear for us because it may cause following situation.
eg.) In case we submit “for approval” document such as Project Master Schedule to Owner, if once Owner approved this schedule, the final document will be submitted as “for reference”.
Could you kindly check and advise how to handle code G documents?