Dear all,
I have some comment in this MOM as follows:
1. Please specify the detail of problem in MOM such as in 2.3) or 3.1) that we have the problem with some pegs were lost or the ID of pegs was different from our data.
2. In the meeting, TRC concern about the outsiders can easily enter the site and will bring to the problem in the future and suggest to build some fence to prevent it but there is some problem with final grading level that still not approve.
Khun Bancha suggest that TRC site team need to make the construction schedule that specify the work plan that the site team need to do step by step and the problem for both TRC and APOT engineer team will acknowledge and know which drawing plan is priority to check and approve to smoothly construction plan in site.
Please include this subject in MOM.