Woravit this should never happen in the first place – please make sure QC are checking the all Valve tags before the client picks it up. Every time this happens we are losing face with the client – at this point of time is not acceptable.
This is such an easy task – E&I Team can complete this and have for the entire project without issues
If your guys cannot complete the works required than replace them!!!! If you won’t then I will!
Further to that – every time I walk into the QC office I see your team playing games on the computers. I understand the works a slowing down but this should only increase our quality level with minimal inspection points.
This will not be tolerated on the Sustain Phase. So please discuss this with your team urgently.