7.6 SEQUENCING
Sequence and coordinate application of sprayed fire-resistive materials
with other related work specified in other Sections to comply with the
following requirements:
7.6.1.1 Provide temporary enclosures for interior applications to
prevent deterioration of fire-resistive material due to
exposure to unfavorable environmental conditions.
7.6.1.2 Avoid unnecessary exposure of fire-resistive material to
abrasion and other damage likely to occur during construction
operations subsequent to its application.
7.6.1.3 Do not apply fire-resistive material to metal roof deck
substrates until roofing has been completed; prohibit roof
traffic during application and drying of fire-resistive
material.
7.6.1.4 Do not begin applying fire-resistive material until clips,
hangers, supports, sleeves, and other items penetrating fire
protection are in place.
7.6.1.5 Defer installing ducts, piping, and other items that would
interfere with applying fire-resistive material until
application of fire protection is completed.
7.6.1.6 Do not install enclosing or concealing construction until after
fire-resistive material has been applied, inspected, tested,
and corrections have been made to defective applications.