1-3 May’15 – 2 POB to Perform 2nd batch survey (Please confirm the duration per result of this survey)
3-7 May’15 – Increase POB to 5 POB (1 Team) to start installation work
8-24 May’15 – Increase POB to 10 POB (2 Teams) to expedite insulation work
24-29 May’15 – Drop 5 POB and complete all jobs on 29 May’15