According to TPT will have new system by test run on Jul’15. And start full option on Oct' 15 TPT will change :
1. P/o :TPT will issue p/o lead time 3 month advance by issue every week.
2. TPT will change" Forecast" to "Information order" 1 month up to lead time of each material .
3. Price: Unit price will fix at issue p/o date .
4. TPT information order, for inform TPT consumption to you prepare material of each month.
And you must be keep TPT consumption, No shortage, Shortage TPT
will charge you and No responsibility material and F/G for discontinue model.
Remark:
Information order :For material are common other company, you can sale your material to other company.
Forecast: In case Unique material or parts ,TPT will responsible material only .
P/o : TPT will responsibility F/G.
Pls. Reply e-mail within 23 Jun.