Auxiliary boiler have step turning burner 11 steps; Now test to step 10 not completed because pressure after PCV under criteria 2.8 barg,.Actually measured step 9 = 3.3 barg. Step 10 = 2.8 barg. (Wait vender adjustment PCV on tomorrow)
Auxiliary boiler have step turning burner 11 steps;Now test to step 10 not completed because pressure after PCV under criteria 2.8 barg,.Actually measured step 9 = 3.3 barg. Step 10 = 2.8 barg. (Wait vender adjustment PCV on tomorrow)