As PISA request to extension to finish work at 31st May 2015 dated 4th February 2014 and have additional cost from delay work as reference 2 We are pleased kindly to inform as below;
1. As PISA’s letter no. 90729_CE_LC_0162 dated 4th February 2014 that request to extension handover work during contraction point no. 2.2, 4 and 5 we considered to submit to employer with attachment file as reference 9.
2. PISA request to extension to finish work at 31st May 2014 disruption due to production slot in the factory being missed, lack of cash-flow disrupting the supply chain, erroneous curved glass NCRs causing delay to installation and late receipt of information. We considered from agreement of contract no.16 there is no reason according to condition of the contract except late receipt of information but you cannot prove that the delay work in the critical path. Therefore, we cannot consider for extension that your request. The reasons for consideration as follows;
2.1 Disruption due to production slot in the factory being missed
Contractor must be responsibility to provide the factory/area to prepare work according contract agreement that to complete work within the time limit.
2.2 Lack of cash-flow
This is contractor internal problems that need to find out the solution to complete work on time. Employer has considered submitting 2nd advance payment and material off-site that additional from contract agreement for help contractor to finish work on time.
2.3 Delay Installation Curved glass
Contractor must be follow to the contract to according with Façade Technical Specifications Clause 215 (B) as reference 3, 4, 5 and 6.
2.4 Late receipt of information
According to details that we receipted we are pleased to consider just critical path work only. Contractor need to submit clarify information of effect to your work.
As PISA request to extension to finish work at 31st May 2015 dated 4th February 2014 and have additional cost from delay work as reference 2 We are pleased kindly to inform as below;
1. As PISA’s letter no. 90729_CE_LC_0162 dated 4th February 2014 that request to extension handover work during contraction point no. 2.2, 4 and 5 we considered to submit to employer with attachment file as reference 9.
2. PISA request to extension to finish work at 31st May 2014 disruption due to production slot in the factory being missed, lack of cash-flow disrupting the supply chain, erroneous curved glass NCRs causing delay to installation and late receipt of information. We considered from agreement of contract no.16 there is no reason according to condition of the contract except late receipt of information but you cannot prove that the delay work in the critical path. Therefore, we cannot consider for extension that your request. The reasons for consideration as follows;
2.1 Disruption due to production slot in the factory being missed
Contractor must be responsibility to provide the factory/area to prepare work according contract agreement that to complete work within the time limit.
2.2 Lack of cash-flow
This is contractor internal problems that need to find out the solution to complete work on time. Employer has considered submitting 2nd advance payment and material off-site that additional from contract agreement for help contractor to finish work on time.
2.3 Delay Installation Curved glass
Contractor must be follow to the contract to according with Façade Technical Specifications Clause 215 (B) as reference 3, 4, 5 and 6.
2.4 Late receipt of information
According to details that we receipted we are pleased to consider just critical path work only. Contractor need to submit clarify information of effect to your work.