5. Spare Part and Consumable
5.1 Initial Spare Part; is the main capital parts provided by the Employer to facilitate such part rotation of the maintenance work of the Contractor ("Initial Spare Part").
(a) The Employer shall provide, free of charge, the capital spare parts and consumables as listed in the table below on or after the Commencement Date ("Initial Spare Part") in accordance with Work Plan as approved by the Employer.
5.2 Critical Spare Part; is critical parts of the Employer's Facility considerably impacted to the performance of the Agreement in the event the Contractor fails to make available at Site ("Critical Spare Part").
(a) The Contractor shall procure the specified part, as listed below, in accordance with the Employer's suggestion for the Vendor's List of such part. In the event the Contractor procure noncompliance part and replace to the Employer's Facility, the Employer may not accept work has been performed by using such part until the Contractor has replaced it with part as suggestion by the Employer.
(b) The Employer may procure Critical Spare Part and store it at the Employer's consignment stock. The Contractor may procure this spare part for the performances of the Contractor and shall reimburse to the Employer, at the items price as to be announced by the Employer, after taking it from the Employer's consignment stock.
(c) At the end of each month, the amount of the spare parts procured by the Contractor from the Employer's consignment stock will be summarized and the Employer shall deduct such reimburse amount from the Contractor's monthly Services Fee in such month ; provided that if such reimbursed amount exceeding than the Service Fee, the Performance Security shall be claimed.
(d) The Contract shall not be claimed for any costs and expenses in the event such Critical Spare Part is not available at the Employer's consignment stock.