4.) Operations and Projects Update/Progress
• 2015 SPH Operation activities and the project updates were presented by PTTEP SP
• 2016 activities were also mentioned to the meeting such as intelligent pigging & Irrigation Dept. will lay water pipeline across SPH’s pipeline
APICO requested short review for the Daily Production Report change/add some line for producing water show negative figures.
PTTP SP mentioned that it was already answered. It was the inspection of the condensate tank and calibration’s accuracy because of draining the water out it will show the negative.