Sale plan
- Mass
1.Accounting section send actual sale since Apr 15 to Nov 15 to CS for send to Customer later (Mass) - Old format with PBP
2.CS Section send mail to Customer
3.Customer send sale plan back to CS
4.K.Falang send sale plan for new project to CS
5.CS-Mass make summary sale plan to Accounting section (include new customer from K.Falang)
6.Accounting separate sale of mass by plan and send to Production plan and Concern section.
7.Review sale plan in Management meeting and send final version after revise (if have)
- RX
1.Budget control send mail to Customer
2.Customer send sale plan back to budget control
3.Budget control make sale plan to Accounting section and PC (include new customer from K.Mazuda) - New format but make by manual
4.Review sale plan in Management meeting and send final version after revise (if have)
Production quantity plan
1.PC section make production quantity plan and send to concern person
2.Present Production plan in meeting (Accounting , PC , Management)
Man Power
1.HR send actual manpower and format for manpower plan to Production
2.Production plan manpower for budget and send to Account & HR
3.Present Manpower plan in Management meeting
Investment Plan
1.Accounting update actual as at Dec'15 then send investment plan to user
2.User distribute investment plan to all concern persons.
3.Present Investment plan in Meeting (Japanese team & Production &Top mangement)
Production cost plan
1. Cost reduction section send Financial Yield plan and Cost reduction plan.
2. Present in meeting Financial Yield plan and Cost reduction plan
Accounting made budget
1. Accounting Mass make HCR and send to K.Panthita
2. K.Panthita make GP Mass
3. Send GP Mass to K.Pinamanee & K.Jummaree for review
4. K.Anchalee make GP RX
5. Send GP RX to K.Pinamanee & K.Jummaree for review
6.Accounting staff make budget
7.Accounting staff send Budget Package by plant to K.Pinmanee & K.Jummaree review
8.Accounting combine budget plan
9.Make Material for budget meeting
10.Meeting with Top management
Submit to GHQ
- Accouting send budget package and material for support meeting to PHQ