All works and design should be carried out in accordance with the requirements for Thailand's Non-Firm SPP project and the current regulations and guidelines for grid connection issued by PEA. The Contractor will cooperate with EGAT and PEA as necessary to achieve timely interconnection, first synchronisation and power quality testing of the plant.
The Contractor is obligated to modify or supply equipment to meet PEA and EGAT requirements for connection and communication under the Contractor’s costs.
Separated auxiliary supply circuit from 22kV PEA’s distribution system shall be provided for internal loads i.e. ventilation system of the inverter house, control room and general purpose under scope of the Contractor. The connection work will be under a separate scope.