Regarding this I discuss with Okada san about current situation NOK capacity difficult to support customer setting volumn around 19,000pcs/month.
If total 21 WD >> Capacity is O.K for 19,000pcs/month.
But NOK need 3 days for washing mold so actual production days is 18 WD >> Capacity around 16,000 pcs/month.
It's dangerous if customer F/C peak more 16,000pcs!
So important thing pls try to check and mornitoring SNSS 's F/C from Apr'15 onward.