This is Ticon property and Makro own the lease, why we don’t have any information? Just understand K.Kittinan approved so then we should not have any issue
I believe there is a protocol we need to follow. By K.Kittinan say yes does not mean you can drop in a new office out of the blue.
Can you answer this
1) Who in Ticon did you inform ?
2) if Ticon charges the rent will DHL pay or Sub con pay?
3) Who will pays the utility cost?
4) How do you control the access, safety and security of this mobile office?
5) How many subcon will install and where will they locate if you have 2-3 more. Now only 2
Point 1,2,3 must be the same at WN
Now Sub con purchase mobile office already. Could you please re consider to approve krub? Now not allow them to work in the office yet till we share how do we control them for safety and security of this mobile office