Dear K. Songphon,
Attached below is the proposed date for maintenance for both MIP & MFC for September, 2557.
Line 5: 2 September. 12 hours stop.
Line 4: 4 September. 16 hours stop.
Line 1: 9 September. 16 hours stop.
MIP: 16 & 17 September 48 hour stop. Major job to replace metering roller.
For your consideration and confirmation on the proposed dates above.
If there are opportunities for stoppage later this month for whatever reason, we will take the opportunity to carry out the maintenance works instead of the proposed dates above.
However, a 3-day notice is necessary in order to get ready the required manpower and parts.