Potonggang have repeatedly ignored the correct protocal proceedure of construction. We have told them that to cast concrete they have to send us the request to inspection; request to cast concrete but to-day they have phone to ask me to inspect the formwork - I refuse because Potonggang did not submit the "request for inspection" and "request to cast concrete" in writting where they have to indicate where they want me to inspect and where they wanted to cast concrete.
At the meeting yesterday we agreed to start casting concrete on Tuesday 16th, then to day they change their mind they wanted to cast concrete tommorrow 14th which is Sunday - fine but then I told themthat I will charge for overtime for the time they are casting concrete for my being there checking that the casting is according to specification, check slump, taking sample for testing and witness their works.