Please be informed that your new annealer is under process of assembly.
We planning to carry out in-house commissioning at the end of this month.
We are hoping to deliver your new annealer to your factory at the end of October if everything goes well.
Therefore, we would like you to prepare utilities for annealer in your factory.
Please find attached piping plan for your preparation.
1) Supply and return of coolant
Demand of supply will be at least 100 L/min. at colder than 25 degree C.
Piping of both of supply and return shall be larger than 1 and 1/2 inch in diameter.
2) Compressed air
Pressure of compressed air shall be at least 0.44 MPa.
Piping of compressed air shall be larger than 3/4 inch in diameter.
3) Nitrogen gas
Purity of Nitrogen gas shall be at least 99.9 vol%.
Demand of Nitrogen gas will be at least 20 L/min.
Piping of Nitrogen gas shall be at least 3/8 inch in diameter.
Furthermore, we modified layout plan of machine.
We changed location of control panel and transformer box on opposite side.
Please find attached layout plan for your approval.