1. SCOPE of SUPPLY
1. Contractor shall be submitted price proposal base on unit rate and reimbursable basis by refer from unit rate (manpower each position rate per day plus overtime rate and mobile equipment rental rate per day).
2. Contractor must be a legal entity registered with the Ministry of Commerce. With registered capital of not less than 5 million baht.
3. Contractor must have experience in the job. Conducted in the Petrochemical and Refinery Turnaround least 5 job and must be evidenced by a certificate or letter from employer contributions to PTT Asahi considered.
4. Contractor must not be on probation or been canceled from the delivery does not meet the requirements or failure to comply with safety rules. Occupational Health and Environmental or impaired performance of petrochemical plants or refineries.
5. Contractor must have a factory license (รง.4) from the provincial Industry and friendly with community include with the evidence of a factory license (รง.4) and a certificate that represents the implementation of the principles of good governance, environment and environmental management systems.
6. Contractor will carry out the Control Valve for overhaul and including auxiliary part replacement as per PTTAC requirement, round the year on annual contract basis.
7. Contractor must be warranty at least 3 month after overhaul and support addition cost in case of found defect from the overhauling, assembly and spare part.
8. The scope of work shall be started from isolation the system, remove control valve, Actuator, final inspection, install control valve, leak test if any, de-isolation shall be responded by Contractor.
8.1 All bolt recheck tightening or replacement of control valve shall be done by Contractor.
8.2 Contractor shall be provided overhaul and testing report including before and after within 3 days.
8.3 Final test and inspection shall be approved by PTTAC staff.
9. Mobile crane for lifting Control valve, blind plate and all covers shall be provided by Contractor.
10. Mobile equipment inspection requirement shall be inspected by PTTAC before using in plant for 1 day.
11. Safety training requirement shall be contact to SHE division for training before start the work for 1 day. And shall submit all staff name list before 1 day as well.
12. Contractor shall be followed the scope of requirement as table from item 3 as per below.
1. SCOPE of SUPPLY1. Contractor shall be submitted price proposal base on unit rate and reimbursable basis by refer from unit rate (manpower each position rate per day plus overtime rate and mobile equipment rental rate per day).2. Contractor must be a legal entity registered with the Ministry of Commerce. With registered capital of not less than 5 million baht.3. Contractor must have experience in the job. Conducted in the Petrochemical and Refinery Turnaround least 5 job and must be evidenced by a certificate or letter from employer contributions to PTT Asahi considered.4. Contractor must not be on probation or been canceled from the delivery does not meet the requirements or failure to comply with safety rules. Occupational Health and Environmental or impaired performance of petrochemical plants or refineries.5. Contractor must have a factory license (รง.4) from the provincial Industry and friendly with community include with the evidence of a factory license (รง.4) and a certificate that represents the implementation of the principles of good governance, environment and environmental management systems.6. Contractor will carry out the Control Valve for overhaul and including auxiliary part replacement as per PTTAC requirement, round the year on annual contract basis. 7. Contractor must be warranty at least 3 month after overhaul and support addition cost in case of found defect from the overhauling, assembly and spare part.8. The scope of work shall be started from isolation the system, remove control valve, Actuator, final inspection, install control valve, leak test if any, de-isolation shall be responded by Contractor. 8.1 All bolt recheck tightening or replacement of control valve shall be done by Contractor.8.2 Contractor shall be provided overhaul and testing report including before and after within 3 days.8.3 Final test and inspection shall be approved by PTTAC staff.9. Mobile crane for lifting Control valve, blind plate and all covers shall be provided by Contractor.10. Mobile equipment inspection requirement shall be inspected by PTTAC before using in plant for 1 day.11. Safety training requirement shall be contact to SHE division for training before start the work for 1 day. And shall submit all staff name list before 1 day as well.12. Contractor shall be followed the scope of requirement as table from item 3 as per below.