Dear Director of TK Mechanical & Electrical,
In regard to this, CSC COMPLEX CENTER.CO,LTD. was notified by TK Mechanical & Electrical of the following:
1. Regarding to find electrical engineering for Validate and monitor about problem electrical system in CSC complex center please be informed that quickly resolve a problem within next week (4/07/2016) or before the time like that:
- Request to move Main distribution board.
- Request to change Air – conditional circuit Breaker.
- Request to change some cable.
- Request to change electrical contractor.
2. In loc.cit. the contract between CSC complex center.Co.Ltd and TK Mechanical & Electrical As for your concern about steps payment we would like to inform that the last payment part of 20% amount $38,689.20 we will paid all after electrical engineering or Technician of TK come to check and resolve our problem finished and than have a contract devolve work to CSC complex center to be a response.
If you can’t resolve in this case our request we will cut the last payment part of 20% amount $38,689.20 to another after electrical engineering for resolve our problems.
We will further liaise with you as soon as possible.
Thank you very much for your kind attention.