Subcontractor shall confirm and sign the Final As-Built BOQ with Contractor for each site before SAC issued. Should there is any decreased or additional work from Initial PO, Subcontractor shall inform Contractor to issue VO accordingly, and process for the second payment after VO issued. There shall be no any additional work accepted and no any VO issued by Contractor after PAC issued.