Sign the new lease and Service Agreement - Already agreed on the details with the landlord
- Get the revised new lease agreement
- The landlord asked to pay the new deposit money for all 6 months first, and then issue
him the official letter to cancel the old lease agreement, to ask him pay back the old
deposit money. The official letter was issued, signed by Kh.Apichai.
- The official letter for cancel the old lease agreement will be submitted to the landlord
on June 2, 2014
Prepare the technical drawing draft - The engineer of the landlord already sent us the technical draft, and I already passed
to APPS and Banzai to consider and give me the feedback.
Propose the technical drawing draft to the - The landlord already proposed the technical drawing to the government officer,
government officer
Finish the full technical drawing This drawing will be used in applying the construction permit and applying
the factory license approval.
Get the construction approval from the To get the feedback / result / approval from the Government Department
government department
Construction - Start the demolish on the old canteen
- Start the construction after get the deposit money from TC Zero
Renovation - APPS proposed the quotation for designing the system to TCZL with amount 95,000
baht. Now, waiting Zero Japan to consider this quotation. Once, this quotation is confirmed,
APPS will send the renovation quotation.
- APPS will step in to renovate overlap together with the construction team
of the landlord. (1.5 months later after the landlord starts the construction)
Apply the construction permit After the full techincal drawing is complete. The landlord will apply the
construction permit.
Apply the factory license approval Once the technical drawing is complete, The officer approves on the construction permit,
we will apply the factory license approval.
Issue PO to Banzai Zero Japan already explained how the maximum capacity for utilization on
this tool and equipment. Kh.Keng Hock will propose and ask for PO approval from
the boss respectively.
- Raise the PO in the system (Tentative schdule)
- Get the PO approval from boss (Tentative schdule)
- Send the PO to Banzai (Tentative schdule)
Importing the equipment Normally, the importing lead-time is 3 months. So, after we can issue PO
to Banzai, we can fix the importing lead-time of this equipment
- Banzai ordering process
- Importing
Importing custom clearance Based on the arrival of the equipment, but normally importing custom
(Tool and equipment) clearance, it takes time for a week.
Arrive at Banzai warehouse Based on the arrival of equipment + importing custom clearance and then
(Tool and equipment) store the equipment at Banzai's warehouse
Tool and Euipment installation Banzai needs the lead time for 1 month for installation the equipment
Apply the buidling use permit This will be done after the construction is complete.
Apply the Factory operating license To get the factory operating license. We need to apply to the Provincical
Industry, to allow us to run body and paint business. This must be apply before
operating the business for 15 days. Need the lead-time for applying this
around 2 weeks.
Apply the Hazardouse to health permit To clarify that our body and paint workshop is not hazardous to health to
the environment.
Sign the new lease and Service Agreement - Already agreed on the details with the landlord
- Get the revised new lease agreement
- The landlord asked to pay the new deposit money for all 6 months first, and then issue
him the official letter to cancel the old lease agreement, to ask him pay back the old
deposit money. The official letter was issued, signed by Kh.Apichai.
- The official letter for cancel the old lease agreement will be submitted to the landlord
on June 2, 2014
Prepare the technical drawing draft - The engineer of the landlord already sent us the technical draft, and I already passed
to APPS and Banzai to consider and give me the feedback.
Propose the technical drawing draft to the - The landlord already proposed the technical drawing to the government officer,
government officer
Finish the full technical drawing This drawing will be used in applying the construction permit and applying
the factory license approval.
Get the construction approval from the To get the feedback / result / approval from the Government Department
government department
Construction - Start the demolish on the old canteen
- Start the construction after get the deposit money from TC Zero
Renovation - APPS proposed the quotation for designing the system to TCZL with amount 95,000
baht. Now, waiting Zero Japan to consider this quotation. Once, this quotation is confirmed,
APPS will send the renovation quotation.
- APPS will step in to renovate overlap together with the construction team
of the landlord. (1.5 months later after the landlord starts the construction)
Apply the construction permit After the full techincal drawing is complete. The landlord will apply the
construction permit.
Apply the factory license approval Once the technical drawing is complete, The officer approves on the construction permit,
we will apply the factory license approval.
Issue PO to Banzai Zero Japan already explained how the maximum capacity for utilization on
this tool and equipment. Kh.Keng Hock will propose and ask for PO approval from
the boss respectively.
- Raise the PO in the system (Tentative schdule)
- Get the PO approval from boss (Tentative schdule)
- Send the PO to Banzai (Tentative schdule)
Importing the equipment Normally, the importing lead-time is 3 months. So, after we can issue PO
to Banzai, we can fix the importing lead-time of this equipment
- Banzai ordering process
- Importing
Importing custom clearance Based on the arrival of the equipment, but normally importing custom
(Tool and equipment) clearance, it takes time for a week.
Arrive at Banzai warehouse Based on the arrival of equipment + importing custom clearance and then
(Tool and equipment) store the equipment at Banzai's warehouse
Tool and Euipment installation Banzai needs the lead time for 1 month for installation the equipment
Apply the buidling use permit This will be done after the construction is complete.
Apply the Factory operating license To get the factory operating license. We need to apply to the Provincical
Industry, to allow us to run body and paint business. This must be apply before
operating the business for 15 days. Need the lead-time for applying this
around 2 weeks.
Apply the Hazardouse to health permit To clarify that our body and paint workshop is not hazardous to health to
the environment.