As per the update given on Friday regarding to the movement plan, Whessoe have arranged for the crane and workers to be at site on Tuesday 28/4/15 morning.
Now with this latest update coming from ARE on the containers leaving LCB today at 11am, has anybody have any update on the movement plan as to when the shipment will be arriving at our Vientiane Workshop, as for us to advise our operation team in Vientiane on the delay of shipment arrival.
There is a cost impact to keep the crane and workers on standby if the shipment is not arriving Vientiane today as per the movement plan which was forwarded on Friday and subsequently been advise to our Vientiane team on Friday.
Kindly advise the statues on the revised movement plan for further advise to our team in Vientiane and to avoid the un-necessary cost impact to be disputed later by both parties.