6.1 Sourcing
6.1.1 Sourcing officer will find out potential supplier and select suppliers based on their ability to
supply products in accordance with the organization's requirements and/or second - third
party audit of supplier sites, when coupled with records of acceptable on the new supplier
approval sheet before put in the AVL and evaluate the performance later
6.1.2 New raw materials/part/components have to conform the part approval work instruction
(WI-EN-013) by engineering team.
6.1.3 Vendor account shall be created by purchaser or supply chain manager. (WI-PU-004)
6.1.4 For direct materials which specified by the customer, The supplier will be automatically in
Approved Vender List but we will evaluate the performance after.
6.1.5 If there is any sub contractor which must be qualified in accordance to the work transfer
process, whenever there is work transfer with sub contractor, subcontractor must get the
re-evaluation.