thank you for your email regarding the payment schedule.
The payment will be ready when your workers will be effectively ready to work at my house. As we have discussed with you before, many times, Romeo and I are tired to chase your teams to come finish their jobs.
The roof structure was finished end of February. Roofing was applied only in May and lasted just 3 days and ceiling can be done in just 4 days. We are NOT HAPPY with this large delay in everything as it is causing us discomfort in our daily life. We also have guests on July 4th and the garden is impracticable and the overall work is just so out of schedule.
We would like to see ALL your TEAMS (especially ceiling technicians and manson technicians) coming to work this week and finish what they have left to do.
If next week CEILING TECHNICIANS are not here yet, we must urge you to call another TEAM or drop the work.