Concrete and Civil works
MDB
Completed install light weight block wall.
Completed wall plastering.
Completed roof steel structure.
Completed provide floor tiles.
Started install roof sheet.
Sound Proof Wall
Completed plastering sound proof wall.
Road (Waiting)
LPG&WATER Pipe foundation (Waiting)
Retaining wall backside (Waiting