Pursuant to clause 22.1 of Conditions of Contract, we hereby issue you the Revision construction drawings of manhole cover relocation for WWTP from L1A on floor under ramp no.2 to L1B on ramp no.2 due to changing type of ramp from one way to two way for you action.