1. To setting budget and cost center for cost booking
- Financial team is accept in principle will support about budget/tracking control budget (Remaining budget of each MOC )
and discuss with K.Sander in the next step per project team ‘s requested.
- Procurement team is require to comparison at least 3 vender for negotiate involve commercial term and will used in case of Plus or Willice (Basket order) for tentative.
- Procurement team is require to QESH for following as safety PTH regulation with outsource contractor (Avoid nearmis accident onsite)
- Time sheet will provide to contractor such summary report per month which T&E will prepare documentation for control time line and project schedule.
- For consumable cost will use lump sun for estimate cost before starting works.