Remarks
1. This quotation is valid within 30 days from the date above
2. This price excluded following expense : Transportation, Accommodation, Hard-copy printing, Signing fee for Engineer and Architect more than 3rd Level ภาคี วิศวกร.
3. The working is subject to extra charge of 2,000 THB/hours when drawing has been changed.
4. Incomplete about design will cause the delay, this quotation included QS work only, Tendering will propose in PM's Quotation.
Period of working
1. 2 Months for permission drawing for IEE
2. 2 Months for tender drawing, after permision dwg. Finished.
3. 1 Month for QS(BOQ) after finishing No.2, This QS scope is not include process of finding contractor
3. 2 Months for construction drawing
Terms Of payment
30% Upon approval or signing order form
30% After IEE submission
30% After completion of Tender drawing
10% After completion of For con drawing