Follow up from 2014 LL meeting
1. List out all MOC, discuss with process and notify MOC owner (MME/Jun 27, 2016)
2. Deep detail hand over between field and planning must be conducted (AWP/MME/OPE/PRS – Jul 8, 2016)
3. Define waste SPOC of process and contact point for maintenance ( Process? /MME maintenance) LYL – Jun 28
4. Interface meeting of maintenance/process and SUP will be held end of Jul 16 after the P6 complete to ensure all parties know the sequence well especially at F3101 (AWP-end of Jul 16)
5. Define cleanliness of decoking with engineer and communicate to worker prior commence the work ( AWP/RCO – end of Jul)