Dear Li Yee and Titus
Apologize for the mistakes about the conclusion. Prince's qualification is unacceptable since they cannot supply base on our proposed tree size.
We agree to include all tenderers to re-submit the tender with Agathis as the base option.
Should we update the BOQ as per our revised external roadside Planting plans (according to URA's requirements) for tenderers to revise and re-submit their tender accordingly ?
Their are some changes to species and quantity of both trees and shrubs which will affect the overall softscape cost.
Thank you
Yes, please update the BOQ including any updated drawings and specifications and revised Tender Questionnaire.
I have revised BOQ.Please find attached BOQ and refer to this updated BOQ.