We hereby serve notice of our intention to seek an extension of time for the Cartier Pavilion Façade Project.
MBM record that the date of possession within the Letter of Award states 14th October 2015, however due to circumstances beyond our control, MBM received possession of the site 4th December 2015 resulting in a delay of 51 days.
MBM record that we will formally submit full and detailed substantiated particulars under a separate cover.
MBM wish to assure the Client that we will endeavor to mitigate the delay to our works to our best means.
Should you have any further queries, please contact the writer.