route1 in Figure 2.39 to Figure 2..41 is probably the least difficult route to manoeuvre. Alternatively route 2 maybe another possible route. We recommended that that EGCO consider carrying out a route survey after feasibility study completion but in advance of EPC contractor procurement, to help define the appropriate access route.