Please find “FABRICATION STATUS REPORT” on THURSDAY 16 JULY 2015 update as above subject for your information.
HIGHLIGHT :
- PROJECT : MODIFY PIPE SUPPORT 52 POINTS AT EGAT ,RECEIVED , Members from Blasting and Painting Shop , Will Packing before shipment tomorrow.
- PROJECT : FABRICATION 4-PIPE SPOOLS , FINISHED , Hydrotest at Pressure 2,350 PSI , Will Blasting and Painting next.
- PROJECT : EXHAUST STACK AND SILENCER , Sent Materials to Blasting and Painting (Primer) on EXPT yard 3 , Prepare Shop Drawing.
- PROJECT : FIRE EXIT PLATFORM (EXPT OFFICE 1) , Finished Conceptual Design , Purchasing Materials , Prepare Shop Drawing.