Refer NPC’s quotation, in part of Onshore Fabrication Work @BPK Yard, item 4 Transport out from Yard It’s clearly defined in RFQ that this is TNS ‘s scope of work.
NPC shall comply with the requirement and withdraw the additional indirect cost.
NPC is required to revise proposal and re-submit.
Any deviations / exception to scope of works shall be considered “Failure to Technical Compliance” and TNS reserve the rights to reject the Proposal