End of March 2015 start civil work. So, we couldn't supply nitrogen gas to Vencorex required date. Because, It have been impacting to our scheduling construction work, such as civil foundation, piping and metering installation, E & I installation including commissioning metering skid and supply Nitrogen to Vencorex. Anyhow could you please extension the schedule for supply Nitrogen to Vencorex plant on the end of June 2015 due to delay for hand over area to us. Anyway PTTME will completed these area and hand over it to us the end of March, then we will start the civil work later. Even though the area hand over by pttme must be accorded to Vencorex civil specification or with soil compaction test report is properly and then we will do quickly to finished whole work within 60 days and Nitrogen wrer supply to Vencorex within proposed time.
If you have any comment or concern please advise to let me know krub. Thank you.