The analysis of results from sections 3 and 4 shows that
results for new integrated ITIL V3 model are pretty better
than for the old one. The time period for the realization of
the old model is 175 days and for the new model is 140
days, so new model is 20% better than the old one. The
similar result has been achieved for the number of
employees that are responsible for the implementation of 2
new services (39 ->30), so new model is 23% better in this
case than the old one. The new ITIL V3 model is better in