Please kindly inform DK, due to the warehouse of this project in Laos is under construction and will take approx.30 days to finish from now so we would ask DK to keep both shipments in DK’s warehouse until we inform to release because we afraid that if the goods arrive site with unsuitable storage place the goods might affect or problem when operate.