With reference to attached report per meeting with your team today. Please expedite to complete touch up work of outstanding unit as follow;
1. Booked unit target completion date :
- 30/09/2015 : #274 #275 - No progress reported as of this week.
- 08/10/2015 : #270 : Delay -7 day from plan due to no 1st floor tile.
- 16/10/2015 : #263 : Delay -5 day from plan due to no interior & exterior paint.
- #246 #250 # 269 : Not enough worker & no progress reported as of this week.
2. Show house #272 : Delay -7 day from plan due to laminated flr & no interior paint.