Number and shall be printed on a single page separated by two vertical
perforations. The PART-I is for de-energisation, the PART-II is for re-
energisation and PART-III is office copy to be retained by the
department of Operation-In-Charge.
2. This Clearance certificate shall be issued in duplicate. (White and Pink
copies). Both the copies to be given to Electrical Operation. On
completion of the job Authorised Person of Electrical Operation shall
sign on both the copies of this certificate and shall return the original
white copy to the section of Operation-In-Charge. Electrical Operation
shall retain the second pink copy.