WHAT DO WE DO NEXT?
2016: Mid of 2016, We approve the 3 years investment plan as:
Jul-Dec 2016:
+Increase the yarn extruder capacity by upgrade screw header from 75mm to be 100mm and increase bobbin wider from 180 bobbins to be 216 bobbins for 3 machines
+ Purchase 2 set of the 2 for 1 ring twist machines
+ Made new ring twist machine 4.5 inch 2 set and 6.0 inch 2 set.
+ Purchase the land and construct 2 factory buildings.
+ Purchase 1 set of the 2.5mts boiler machine.