Commercial Term
CONTRACTOR shall provide a Lump Sum Price in Thai Baht with supporting details including breakdown of unit rate.
CONTRACTOR must understand that COMPANY does not bind itself to accept the lowest or any quotation, and reserves the right to accept a portion of any quotation, unless the CONTRACTOR expressly stipulates otherwise in their quotation and the CONTRACTOR shall agree that PTTEP decision shall not be contested or opposed.
Any delay schedule caused by CONTRACTOR’s mistakes, low performance and unacceptable quality cannot be charged back to COMPANY.
CONTRACTOR shall be responsible for all costs and expenses for transportation of Equipment, Fabricated material to COMPANY’s jetty in SONGKHLA.
CONTRACTOR shall be entitled to place the invoice only when he has completed the work and all liabilities as specified in the consequent SERVICE ORDER and COMPANY has issued to him the COMPLETION CERTIFICATE.