the contractor agrees to complete the work as called for under this contract within june 3 2015
failure on part of the contractor to complete the work within the time specified above plus any extension thereof authorized by egat. egat reserves the right to impose the liquidated damages for late completetion as per Article F-15. of special conditions in the contract documents.