All the projects will be undertaken except for project 8 since it is mutually exclusive with project 7, and project 6 and 2 will not be undertaken since they have IRR that is less than the 10%, the discount rate. Project 1 also might not be taken since “certain officers of the company have recently asserted that the discount rate should be much higher.”